Lean construction
value stream mapping benefits in the procurement department of a construction company
DOI:
https://doi.org/10.14488/BJOPM.3066.2026Keywords:
Lean construction, Procurement, Value stream map, Quality management, Supply chainAbstract
Goal: the purpose of this study was to report how the use of Lean Construction tools helped the procurement department of a medium-sized Brazilian construction company to reduce the lead time of delivered materials on the site, during the COVID-19 pandemic.
Design / Methodology / Approach: this applied research adopts both exploratory and descriptive objectives, utilizing a qualitative case study strategy. Data collection involved triangulating sources such as documents, interviews, and field observations.
Results: the current Value Stream Map (VSM) pointed out that takt time of material requisitions received per day (RPD) is faster than the pace of the procurement stream. The future VSM simulated with an additional employee showed that it would be possible to reach an effective capacity of 10 RPD, meeting the engineering department’s demand, with lead time reduction from 84 to 49.5 hours.
Limitations of the investigation: the primary limitation concerns the generalizability of the conclusions, models, or theories derived from this single case study. Nonetheless, these constraints do not diminish the significance of the findings, which contributed to the company's decision to employ an additional staff member in the procurement department.
Practical implications: the procedures used in this study—including takt time calculation, processing time analysis, and the development of current and future-state VSMs—can be applied by other organizations to reduce value-stream lead times.
Originality / Value: this research differs from existing studies by combining VSM, takt time and lead time in the procurement department of a construction company.
Downloads
References
Agência Brasil (2024), “Mesmo na pandemia, emprego na construção cresceu 21,6%, revela IBGE”, available at: https://agenciabrasil.ebc.com.br/economia/noticia/2024-05/mesmo-na-pandemia-emprego-na-construcao-cresceu-216-revela-ibge (accessed 5 August 2024)
Alvarez, R. dos R. and Antunes Jr, J.A.V. (2001), “Takt-time: concepts and context in Toyota Production System”, Gestão & Produção, v. 8, n.1, p. 1-18, available at: https://www.scielo.br/j/gp/a/RZFdSpRQdjVmWcjT6ZCLJnM/?format=pdf&lang=pt (accessed 3 May 2025).
Arbulu, R., Tommelein, I., Walsh, K. and Hershauer, J. (2003), “Value stream analysis of a re-engineered construction supply chain”, Building Research & Information, 31(2), 161–171, https://doi.org/10.1080/09613210301993.
Barkokebas, B., Khalife, S., Al-Hussein, M. and Hamzeh, F. (2021), “A BIM-lean framework for digitalisation of premanufacturing phases in offsite construction”, Engineering, Construction and Architectural Management, Vol. 28 No. 8, pp. 2155-2175, https://doi.org/10.1108/ECAM-11-2020-0986.
Borges, G.A. and Regattieri, C.R. (2018), “Productive stock management reorganizing the layout using the method systematic and simplified planning of layout (SSLP) for an efficient lead time: case study in a distributor of drawn tubes and solid steels for hydraulic cylinders”, Revista Interface Tecnológica, Taquaritinga, SP, v. 15, n. 1, p. 385–397, https://doi.org/10.31510/infa.v15i1.329.
Creswell, J.W. (2009), Qualitative, Quantitative and Mixed Methods Approaches, 3rd Edition, Sage Publications, Inc.
De Souza Pinto, J., Aoki Schuwarten, L., Cassoli de Oliveira Júnior, G. and Novaski, O. (2017), “Proposal the application of DMAIC tools and value stream mapping under the perspective of the lean philosophy for process improvement: a case study”, Brazilian Journal of Operations & Production Management, 14(4), 556–566, https://doi.org/10.14488/BJOPM.2017.v14.n4.a11.
Eugênio, C.A. and Bonette, L.R. (2019), “Lead time case study of a center for production and reverse distribution of wooden pallets in the Bebedouro region of São Paulo”, SITEFA, 2(1), 457–466, https://doi.org/10.33635/sitefa.v2i1.80.
Euphrosino, C.A., Pimentel, L.L., Camarini, G., Ortigara, Y.V.B., Ruiz, P.V. and Fontanini, P.S.P. (2019), “Soil-cement masonry brick production and construction process mapping for social interest housing”, Revista Matéria, v. 24, n. 4, https://doi.org/10.1590/S1517-707620190004.0848.
Favoni, C., Gambi, L. do N. and Careta, C.B. (2013), “Opportunities for implementation of concepts and tools lean production aiming to improve competitiveness of enterprises of shoe APL Jaú/SP”, Revista Produção Online, 13(3), 1118-1142, https://doi.org/10.14488/1676-1901.v13i3.1404.
Fourie, C.J. and Umeh, N.E. (2017), “Application of Lean tools in the supply chain of a maintenance environment”, South African Journal of Industrial Engineering, Vol 28(1), pp 176-189, https://doi.org/10.7166/28-1-1507.
Gnanavel, S.S., Balasubramanian, V. and Narendran, T.T. (2015), “Suzhal – An alternative layout to improve productivity and worker well-being in labor demanded Lean environment”, Procedia Manufacturing, v. 3, p.574-580, https://10.1016/j.promfg.2015.07.268.
Gomes, E.R.L. (2019), Lean Construction como ferramenta de controle e economia de materiais em obras: uma revisão bibliográfica, Trabalho de conclusão de curso (graduação em Engenharia Civil), Centro Universitário Unifacig, Manhuaçu, 25 p, available at: https://pensaracademico.unifacig.edu.br/index.php/repositoriotcc/article/view/1793 (accessed 3 May 2025).
Gomes, R.G.B. (2013), Aplicabilidade do programa Lean Seis Sigma na redução do Lead Time de licitações de obras e serviços de engenharia, Dissertação (mestrado) - Universidade Federal de Minas Gerais, 114 p, available at: https://repositorio.ufmg.br/bitstream/1843/ISMS-97RKCG/1/rosemary_geralda_barbosa_gomes__final_com_ficha_catalogr__fica_.pdf (accessed 3 May 2025).
Grant, M.J. and Booth, A. (2009), “A typology of reviews: an analysis of 14 review types and associated methodologies”, Health Information & Libraries Journal, 26: 91-108. https://doi.org/10.1111/j.1471-1842.2009.00848.x.
Issa, U.H. and Alqurashi, M. (2020), “A model for evaluating causes of wastes and Lean implementation in construction projects”, Journal of Civil Engineering and Management, 26(4):331-342, https://doi.org/10.3846/jcem.2020.12323.
Koskela, L. (1992), Application of the New Production Philosophy to Construction, Technical Report # 72, Center for Integrated Facility Engineering, Department of Civil Engineering, Stanford University, CA, available at: https://www.researchgate.net/profile/Lauri-Koskela-2/publication/243781224_Application_of_the_New_Production_Philosophy_to_Construction/links/5bcd97a792851cae21b8dd9a/Application-of-the-New-Production-Philosophy-to-Construction.pdf (accessed 3 May 2025).
LIB - Lean Institute Brasil (2016), Mapeamento do Fluxo de Valor – Serviços e Processos Administrativos, Workshop in-company.
Lucena, A.F.E. and De Mori, L.M. (2018), “Critical analysis of Lean Construction measuring tools”, Brazilian Journal of Operations & Production Management, 15(2), 311–321, https://doi.org/10.14488/BJOPM.2018.v15.n2.a13.
Marconi, M. de A. and Lakatos, E.M. (2019), Fundamentals of scientific methodology, 8.ed. São Paulo: Atlas.
Mariz, R.N. and Picchi, F.A. (2014), “Production cell implementation in the facade execution: a construction case study”, Revista Produção Online, 14(2), 703–719, https://doi.org/10.14488/1676-1901.v14i2.1499.
Melo, M., Deschamps, F. and Costa, S. E. G. da. (2017), “Application of Lean Construction − A Systematic Literature Review”, Journal of Lean Systems, v. 2, n. 3, available at: https://ojs.sites.ufsc.br/index.php/lean/article/view/1639 (accessed 3 May 2025).
Moraes, A. M. de. and Fonseca, J. J. S. da (2017), Metodologia da Pesquisa Científica, 1. Ed. Sobral, cap. 1, p. 102-126, 117, available at: https://dirin.s3.amazonaws.com/drive_materias/1649850285.pdf (accessed 3 May 2025).
Muralidhar, P. (2018), “Analysis on improving operational efficiency of construction project site”, Independent Journal of Management & Production, v. 9, n. 3, https://doi.org/10.14807/ijmp.v9i3.686.
Nery, V. F. e S. de O, Zattar, I. C. and Oliveira, V. O. de. (2017), “Application of Lean Construction Philosophy in the Productive Process of a Civil Construction Sector’s Company”, Exacta, 15(4), https://doi.org/10.5585/exactaep.v15n4.7107.
Oliveira, B.F., Freitas, M.C.D., Hofacker, A., Gehbauer, F. and Mendes Júnior, R. (2010), “Um modelo de avaliação do grau de aplicação de Ferramentas Lean em empresas construtoras: o rapid Lean Construction-quality rating Model (LCR)”, Revista Iberoamericana de Engenharia Industrial, v. 2, n. 2, p. 156-174, https://doi.org/10.13084/2175-8018.v02n04a08.
Pepper, M.P.J. and Spedding, T.A. (2010), "The evolution of lean Six Sigma", International Journal of Quality & Reliability Management, Vol. 27 No. 2, pp. 138-155. https://doi.org/10.1108/02656711011014276.
Pfaffenzeller, M.S., Silva, G.G.M.P. da, Barros, A.L. de, Shinji, G. and Salles, M.P. (2015), “Lean Thinking na Construção Civil: Estudo da Utilização de Ferramentas da Filosofia Lean em Diferentes Fluxos da Construção Civil”, Iberoamerican Journal of Industrial Engineering, Florianópolis, SC, Brasil, v. 7, n. 14, p. 86-107, available at: https://periodicos.ufsc.br/index.php/IJIE/article/view/104481/pdf_106 (accessed 3 May 2025).
Pires, M.M. de O. and Fontanini, P.S.P. (2017), “Análise do processo construtivo do sistema PVC concreto para abrigo de equipamentos – um estudo de caso de mapeamento de fluxo de valor”, in Anais [...]. Porto Alegre: ANTAC, 2017, https://doi.org/10.17648/tecsic-2017-72103.
Rech, A., Fleig, R., Cembranel, P.A., Nascimento, I.B. do and Keine, S. (2019), “Application of value flow mapping in the manufacturing of the platform used in civil construction”, Produto & Produção, v. 20, n. 3, https://doi.org/10.22456/1983-8026.94010.
Salifu-Asubay, E.K. and Adjei Mensah, C. (2015), “Improving Delivery of Construction Projects in Ghana’s Cities: A Lean Construction Approach”, International Journal of Sustainable Construction Engineering and Technology, 6(1), 1-15. https://penerbit.uthm.edu.my/ojs/index.php/IJSCET/article/view/993.
Sehnem, E.H., Kipper, L.M., Silva, J.I. da, Freitas, F. de and Choaire, G.T. (2020), “Utilization of the Lean manufacturing principles and value stream mapping for identification of waste in the finished product stock”, Exacta, 8(1), 165–184, https://doi.org/10.5585/exactaep.v18n1.8629.
Tomioka, A.M., Leite, J. de S., Neves, J.M.S. das and Silva, M.L.P. da (2020), “Lean Philosophy in Brazilian Industry: Literature Review”, Brazilian Journal of Development, 6(3), 11823–11843, https://doi.org/10.34117/bjdv6n3-154.
Turrioni, J.B. and Mello, C.H.P. (2012), Research methodology in production engineering: strategies, methods, and techniques for conducting quantitative and qualitative research, Programa de Pós-graduação em Engenharia de Produção, Universidade Federal de Itajubá, Itajubá.
Vatne, M.E. and Drevland, F. (2016), “Practical benefits of using Takt Time Planning: A Case study”, Proc. 24th Ann. Conf. of the Int’l. Group for Lean Construction, Boston, MA, USA, sect.6 pp. 173–182, available at: www.iglc.net (accessed 3 May 2025).
Vivan, A.L., Ortiz, F.H. and Paliari, J.C. (2012), “Parâmetros de eficácia na aplicação de ferramentas Lean a partir da análise do mapeamento de fluxo de valor”, In: XIV ENTAC - Encontro Nacional de Tecnologia do Ambiente Construído, 29 a 31 Outubro, Juiz de Fora Anais... Porto Alegre: ANTAC, 2012.
Voss, C., Tsikriktsis, N. and Frohlich, M. (2002), “Case research in operations management”, International Journal of Operations & Production Management, v. 22, n.2, p. 195-219, https://doi.org/10.1108/01443570210414329.
Werkema, C. (2012), Lean seis sigma: introdução às ferramentas do lean manufacturing, 2. ed. Rio de Janeiro: Elsevier.
Womack, J.P. and Jones, D.T. (2003), Lean Thinking: banish waste and create wealth in your corporation, Free Press, New York.
Woodside, A.G. and Wilson, E.J. (2003), “Case studies research methods for theory building”, Journal of Business and Industrial Marketing, v. 18, n. 6/7, p. 493-508. http://dx.doi.org/10.1108/08858620310492374.
Yin, R.K. (2015), Case Study Research, 5th Edition, Sage Publications, Inc.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Paloma Garrido Correia Teles, Alberto Eduardo Besser Freitag, Marcelle Candido Cordeiro, Marcelo Jasmim Meiriño

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors must have a written permission from any third-party materials used in the article, such as figures and graphics. The permission must explicitly allow authors to use the materials. The permission should be submitted with the article, as a supplementary file.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) after BJO&PM publishes it (See The Effect of Open Access).